Backstage Construction UPDATE – June 20 – 21

This is an update for the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 20 – 21, 2013

Please click here for general information on concrete pours.

Updated June 19.

Thursday, June 20

  • Concrete pour #4 for parking level 3, by subcontractor ItalformThe pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

Friday, June 21

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction UPDATE June 20-21-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: