Backstage Construction Schedule – June 15 – 21
June 14, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for June 15 – 21, 2013
Please click here for general information on concrete pours.
Updated June 14.
Saturday, June 15
- General clean up on the site by Domninus and Italform.
Monday, June 17
- Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform.The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.
Tuesday, June 18
- There will be a rebar delivery at 7:00 am.
- Concrete pour #3 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Wednesday, June 19
- Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.
Thursday, June 20
- Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.
Friday, June 21
- There will be a rebar delivery at 7:00 am.
- Concrete pour #4 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 15-21-2013