Backstage Construction Schedule – June 15 – 21

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 15 – 21, 2013

Please click here for general information on concrete pours.

Updated June 14.

Saturday, June 15

  • General clean up on the site by Domninus and Italform. 

Monday, June 17

  • Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform.The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, June 18

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #3 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, June 19

  • Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Thursday, June 20

  • Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Friday, June 21

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #4 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 15-21-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: