Backstage Construction Update for June 11
June 10, 2013 Leave a comment
This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium – for June 11, 2013
Please click here for general information on concrete pours.
Posted June 10.
Tuesday, June 11
- There will be a rebar delivery at 7:00 am.
- The Parking Level 3 concrete pour originally scheduled for Monday June 10 was cancelled due to rain and has been rescheduled to today —— Concrete pour #1 for parking level 3, by subcontractor Italform. The pour is now scheduled to begin at 9:30 am and concrete finishing should be completed no later than 10:00 pm.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
- Please click here for the balance of the week’s construction schedule
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.