Backstage Construction Schedule – July 2 – 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  July 2 – 5, 2013

Please click here for general information on concrete pours.

Posted June 28.

Monday, July 1 – Happy Canada Day

  • Site closed for the holiday.

Tuesday, July 2

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #7 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, July 3

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Thursday, July 4

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Friday, July 5

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #1 for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A  50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary July 2-5-2013

L Tower Construction Schedule July 2 – 5

This is the current construction schedule for 8 The Esplanade – L Tower –  July 2 – 5,  2013

Posted June 28, 2013

Monday July 1 – Happy Canada Day

  • Construction site closed for the holiday

Tuesday, July 2

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, July 3

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, July 4

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, July 5

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary July 2-5-2013

Backstage Concrete Pour UPDATE – June 24

This is an update for the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 24, 2013

Please click here for general information on concrete pours.

Updated June 24.

Monday, June 24

  • Please be advised that because of this afternoon’s rain, concrete finishing at Backstage will unfortunately go past 10:00 pm tonight. Every effort will be made to complete the work as soon as possible. 
     
    We apologize for any inconvenience this may cause and thank you in advance for your kind understanding. 

Backstage Construction Schedule – June 22 – 28

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 22 – 28, 2013

Please click here for general information on concrete pours.

POSTED June 21.

Saturday, June 22

  • General clean up on the site by Domninus.

Monday, June 24

  • Concrete pour #7 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, June 25

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #5 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, June 26

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Thursday, June 27

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Friday, June 28

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #6 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 22-28-2013

L Tower Construction Schedule June 24 – 28

This is the current construction schedule for 8 The Esplanade – L Tower –  June 24 – 28, 2013

Posted June 21, 2013

Monday, June 24

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, June 25

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, June 26

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, June 27

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, June 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 22-28-2013

Backstage Concrete Pour UPDATE – June 20

This is an update for the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 20, 2013

Please click here for general information on concrete pours.

Updated June 20.

Thursday, June 20

  • Concrete pour #4 for parking level 3, by subcontractor ItalformThe pour that was scheduled to begin at 10:00 am began later today, due to concrete delivery problems earlier in the day that were beyond the control of the construction team, concrete finishing is now expected to go past 10:00 pm tonight, and is anticipated to go to as late as 12:00 am – Midnight.
  • On behalf of the construction team please accept our apology for any inconvenience this may cause.
  • Please note that a continuous concrete pour and the concrete finishing that is required immediately following pouring must continue until the work is complete. If one were to stop and start pours and finishing, floors would not be even, columns would not set properly, putting the structural soundness of the building at risk.

Backstage Construction UPDATE – June 20 – 21

This is an update for the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 20 – 21, 2013

Please click here for general information on concrete pours.

Updated June 19.

Thursday, June 20

  • Concrete pour #4 for parking level 3, by subcontractor ItalformThe pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

Friday, June 21

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction UPDATE June 20-21-2013

Backstage Construction Schedule – June 15 – 21

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 15 – 21, 2013

Please click here for general information on concrete pours.

Updated June 14.

Saturday, June 15

  • General clean up on the site by Domninus and Italform. 

Monday, June 17

  • Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform.The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, June 18

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #3 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, June 19

  • Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Thursday, June 20

  • Forming plus a 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Friday, June 21

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #4 for parking level 3, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 15-21-2013

L Tower Construction Schedule June 17 – 21

This is the current construction schedule for 8 The Esplanade – L Tower –  June 17 – 21, 2013

Posted June 14, 2013

Monday, June 17

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, June 18

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, June 19

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, June 20

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, June 21

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 15-21-2013

Backstage Construction Update for June 11

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  June 11, 2013

Please click here for general information on concrete pours.

Posted June 10.

Tuesday, June 11

  • There will be a rebar delivery at 7:00 am.
  • The Parking Level 3 concrete pour originally scheduled for Monday June 10 was cancelled due to rain and has been rescheduled to today —— Concrete pour #1 for parking level 3, by subcontractor Italform. The pour is now scheduled to begin at 9:30 am and concrete finishing should be completed no later than 10:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.