Backstage Construction Schedule – June 3 – 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May June 3 – 7, 2013

Please click here for general information on concrete pours.

Posted May 31

Monday, June 3

  • Concrete pour #6 for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Tuesday, June 4

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Wednesday, June 5

  • Concrete pour #7 for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Thursday, June 6

  • Concrete pour #6 – part 2, for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Friday, June 7

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 3-7-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: