Backstage Construction Schedule – June 3 – 7
May 31, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for May June 3 – 7, 2013
Please click here for general information on concrete pours.
Posted May 31
Monday, June 3
- Concrete pour #6 for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.
Tuesday, June 4
- There will be a rebar delivery at 7:00 am.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.
Wednesday, June 5
- Concrete pour #7 for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.
Thursday, June 6
- Concrete pour #6 – part 2, for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.
Friday, June 7
- There will be a rebar delivery at 7:00 am.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary June 3-7-2013