Backstage Construction Schedule – May 21 – 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 21 – 24, 2013

Please click here for general information on concrete pours.

Posted May 17

Monday, May 20 – Victoria Day Holiday

Tuesday, May 21

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, May 22

  • There will be a rebar delivery at 7:00 am.
  • The third concrete pour for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

Thursday, May 23

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, May 24

  • There will be a rebar delivery at 7:00 am.
  • The fourth concrete pour for parking level 4, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary May 20-24-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: