Backstage Construction Schedule – May 6 – 10
May 3, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for May 6 – 10, 2013
Please click here for general information on concrete pours.
Posted May 3
Monday, May 6
- The concrete pour for the garage ramp slab, by subcontractor Italform.The pour is scheduled to begin at 10:30 am and concrete finishing should be completed no later than 10:00 pm.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.
Tuesday, May 7
- There will be a rebar delivery at 7:00 am.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.
Wednesday, May 8
- The sixth concrete pour for parking level 5, by subcontractor Italform. The pour is scheduled to begin at 10:30 am and concrete finishing should be completed no later than 9:30 pm.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.
Thursday, May 9
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.
Friday, May 10
- There will be a rebar delivery at 7:00 am.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary May 6-10-2013