Updated – Backstage Construction Schedule – May 2 – 3

This is the updated construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  May 2 to May 3, 2013

Please click here for general information on concrete pours.

UPDATED MAY 1

Thursday, May 2

  • RESCHEDULED from Tuesday April 30 to today:
    The fifth concrete pour for parking level 5, by subcontractor Italform.
    The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • UPDATED: A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Friday, May 3

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryUPDATED Backstage & L Tower Construction Summary May 2-3-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: