Update for Backstage Construction Schedule – April 5 & 6

This is the update t the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 5 – 6, 2013

Updated April 5 –  2013

Friday, April 5 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • Italform will be pouring parking level 5–pour #1. This pour will start at 9:30am and will take approximately 3 hours to place the concrete. It is anticipated that the concrete finishing will go to 10:30 pm.

Saturday, April 6 – Daytime Vehicular Road Closure

  • GFL Excavating will hoisting excavators out of the excavation to facilitate this Dominus is applying for a vehicular road closure on The Esplanade from Yonge Street to Scott Street. Domius has also requested two paid duty officers.
  • The hoisting operation is estimated to start at 9:00am and go to 1:00pm

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: 

Backstage Construction Schedule – April 3 – 6, 2013 – Updated

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 3 – 6, 2013

Updated April 5 –  2013

Wednesday, April 3 – – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will extend to at least  8:30 pm this evening.

Thursday, April 4 

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions. 

Friday, April 5 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • Italform will be pouring parking level 5–pour #1. This pour will start at 9:30am and will take approximately 3 hours to place the concrete. It is anticipated that the concrete finishing will go to 10:30 pm.

Saturday, April 6 – Daytime Vehicular Road Closure

  • GFL Excavating will hoisting excavators out of the excavation to facilitate this Dominus is applying for a vehicular road closure on The Esplanade from Yonge Street to Scott Street. Domius has also requested two paid duty officers.
  • The hoisting operation is estimated to start at 9:00am and go to 1:00pm

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: 

L Tower Construction Schedule April 1 – 5

This is the current construction schedule for 8 The Esplanade – L Tower –  April 1 – 5, 2013

Posted March 28, 2012

MondayApril 1

  • Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.  

Tuesday, April 2

  • Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.  

Wednesday, April 3

  • Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.  

Thursday, April 4

  • Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.  

Friday, April 5

  • Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.  

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary April 1-5-2013

Backstage Construction Schedule – April 1 – 5, 2013 – Updated

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 1 65, 2013

Updated April 3 –  2013

Monday, April 1

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions. 

Tuesday, April 2

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions. 

Wednesday, April 3 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will extend to at least  8:30 pm this evening.

Thursday, April 4 

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions.

Friday, April 5

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour may extend later than 7:00 pm, subject to weather conditions. 

Saturday, April 6 – Daytime Vehicular Road Closure – click here for details

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary April 1-5-2013

UPDATE: Site work has resumed at Backstage / L Tower Parking

UPDATE: The injured worker has been taken to hospital, and pedestrian access through the site is open. Vehicular traffic is restricted. Work has resumed on-site. Thank you for your understanding.

Worker injured on-site in collision at L Tower Parking site

April 1, 2016 – 2:20 pm

We regret to advise that a traffic coordinator at the L Tower Parking / Backstage condominium construction site has been injured  in a collision with a motor vehicle (which may have been a commercial taxi). Police and EMS are on site. We expect the job-site to close down, at least temporarily.