Backstage Construction Schedule – April 29 – May 3
April 26, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for April 29 – May 3, 2013
Please click here for general information on concrete pours.
UPDATED MAY 1
Monday, April 29
- A slab concrete pour on grade, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:00 pm.
Tuesday, April 30
- There will be a rebar delivery at 7:00 am.
- CANCELLED & RESCHEDULED to May 2— The fifth concrete pour for parking level 5, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:00 pm.
Wednesday, May 1
- A slab concrete pour on grade, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:00 pm.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Thursday, May 2
- RESCHEDULED from Tuesday to today: The fifth concrete pour for parking level 5, by subcontractor Italform.
The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- UPDATED: A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.
Friday, May 3
- There will be a rebar delivery at 7:00 am.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary April 29-May 3-2013