This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium – for April 26, 2013
Please click here for general information on concrete pours.
Updated April 25, 2013
Friday, April 26
- The fourth concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 9:00 am and should be completed as early as 9:00 pm but no later than 10:00 pm.
- A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.
- The rebar delivery originally scheduled for 7:00 am has been rescheduled to Monday April 29.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.