Backstage Construction Schedule – April 22 – 26

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 22 – 26, 2013

Please click here for general information on concrete pours.

Updated April 25, 2013

Monday, April 22

  • The third concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed no later than 10:30 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Tuesday, April 23

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Wednesday, April 24

  • The fourth concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed no later than 10:30 pm..
  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Thursday, April 25

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Friday, April 26

  • The fourth concrete pour for parking level 5 by subcontractor ItalformThe pour is scheduled to begin at 9:00 am and should be completed as early as 9:00 pm but no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary April 22-26-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: