Backstage Construction Schedule – April 15 – 19
April 12, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for April 15 – 19, 2013
Please click here for general information on concrete pours.
Posted April 12, 2013
Monday, April 15
- There will be a rebar delivery at 7:00 am.
- A slab on grade concrete pour by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed by 10:30 pm.
Tuesday, April 16
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour is scheduled to begin at 12:30 pm and should be completed prior to 8:00 pm.
Wednesday, April 17
- There will be a rebar delivery at 7:00 am.
- A slab on grade concrete pour by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed by 8:30 pm.
Thursday, April 11
- A concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed by 10:30 pm.
Friday, April 12
- There will be a rebar delivery at 7:00am.
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour is scheduled to begin at 12:30 pm and should be completed prior to 8:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.