Backstage Construction Schedule – April 15 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 15 – 19, 2013

Please click here for general information on concrete pours.

Posted April 12, 2013

Monday, April 15

  • There will be a rebar delivery at 7:00 am.
  • A slab on grade concrete pour by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed  by 10:30 pm.

Tuesday, April 16

  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour is scheduled to begin at 12:30 pm and should be completed prior to 8:00 pm.

Wednesday, April 17

  • There will be a rebar delivery at 7:00 am.
  •  A slab on grade concrete pour by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed by 8:30 pm.

Thursday, April 11

  • A concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed  by 10:30 pm.

Friday, April 12

  • There will be a rebar delivery at 7:00am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour is scheduled to begin at 12:30 pm and should be completed prior to 8:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary:

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: