Update for Backstage Construction Schedule – April 5 & 6

This is the update t the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 5 – 6, 2013

Updated April 5 –  2013

Friday, April 5 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • Italform will be pouring parking level 5–pour #1. This pour will start at 9:30am and will take approximately 3 hours to place the concrete. It is anticipated that the concrete finishing will go to 10:30 pm.

Saturday, April 6 – Daytime Vehicular Road Closure

  • GFL Excavating will hoisting excavators out of the excavation to facilitate this Dominus is applying for a vehicular road closure on The Esplanade from Yonge Street to Scott Street. Domius has also requested two paid duty officers.
  • The hoisting operation is estimated to start at 9:00am and go to 1:00pm

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: