Backstage Construction Schedule – April 8 – 12
April 5, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for April 8 – 12, 2013
Posted April 5, 2013
Monday, April 8
- Dominus will receive gravel for the slab on the lowest grade base. One dump truck will be working throughout the day approximately 8 loads of gravel.
- There will be a rebar delivery at 11:00am.
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.
Tuesday, April 9
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.
Wednesday, April 10
- There will be a rebar delivery at 11:00am.
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.
Thursday, April 11
- A parking level pour by subcontractor Italform, 80 meters of concrete starting at 9:30am.
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.
Friday, April 12
- There will be a rebar delivery at 7:00am.
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary April 8-12-2013