L Tower Construction Schedule April 1 – 5
April 3, 2013 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – April 1 – 5, 2013
Posted March 28, 2012
Monday, April 1
- Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.
- Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.
Tuesday, April 2
- Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.
- Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.
Wednesday, April 3
- Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.
- Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.
Thursday, April 4
- Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.
- Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.
Friday, April 5
- Subcontractor Premform demobilizing form panels and related equipment from the building site and transporting them off-site. Trucks will be arriving to take the material away. There may be short-term disruptions to traffic adjacent to the site.
- Deliveries of materials and supplies to the hoist throughout the day, starting at 7:00 am.
Please note:
- There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary April 1-5-2013