Backstage Construction Schedule – April 29 – May 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 29 – May 3, 2013

Please click here for general information on concrete pours.

UPDATED MAY 1

Monday, April 29

  • A slab concrete pour on grade, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:00 pm.

Tuesday, April 30

  • There will be a rebar delivery at 7:00 am.
  • CANCELLED & RESCHEDULED to May 2— The fifth concrete pour for parking level 5, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:00 pm.

Wednesday, May 1

  • A slab concrete pour on grade, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 9:00 pm.
  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, May 2

  • RESCHEDULED from Tuesday to today: The fifth concrete pour for parking level 5, by subcontractor Italform.
    The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • UPDATED: A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 1:30 pm and should be completed no later than 7:00 pm.

Friday, May 3

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary April 29-May 3-2013

L Tower Construction Schedule April 29 – May 3

This is the current construction schedule for 8 The Esplanade – L Tower –  April 29 – May 3, 2013

Posted April 26, 2013

Monday, April 29

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, April 30

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, May 1

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, May 2

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, May 3

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction  work inside the L Tower. 

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary April 29-May 3-2013

Backstage Construction Update for April 26

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  April 26, 2013

Please click here for general information on concrete pours.

Updated April 25, 2013

Friday, April 26

  • The fourth concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 9:00 am and should be completed as early as 9:00 pm but no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.
  • The rebar delivery originally scheduled for 7:00 am has been rescheduled to Monday April 29.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – April 22 – 26

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 22 – 26, 2013

Please click here for general information on concrete pours.

Updated April 25, 2013

Monday, April 22

  • The third concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed no later than 10:30 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Tuesday, April 23

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Wednesday, April 24

  • The fourth concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed no later than 10:30 pm..
  •  A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Thursday, April 25

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

Friday, April 26

  • The fourth concrete pour for parking level 5 by subcontractor ItalformThe pour is scheduled to begin at 9:00 am and should be completed as early as 9:00 pm but no later than 10:00 pm.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summaryBackstage & L Tower Construction Summary April 22-26-2013

L Tower Construction Schedule April 22 – 26

This is the current construction schedule for 8 The Esplanade – L Tower –  April 22 – 26, 2013

Posted April 19, 2013

Monday, April 22

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower.

Tuesday, April 23

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower.

Wednesday, April 24

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower.

Thursday, April 25

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower.

Friday, April 26

  •  There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower. 

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary April 22-26-2013

Long Reach Excavator to be removed Friday 4 am – 5:30 am

Please Note: the Backstage & L Tower Parking Construction site managers have just been advised this evening that the Long Reach Excavator may be removed from the construction site early Friday morning. 
 
We expect that the removal will be between 4:00 am and 5:30 am, Friday April 19 – under police escort.
 
Toronto Police Services will not permit the large 32-axle semi-trailer, which is required to take away the Long Reach, to be on city streets during rush hour nor during regular daytime traffic. 
 
We apologize for any inconvenience and for the short notice. Please be assured that all reasonable attempts had been made to seek more advance notice.
 
We will update information as soon as we receive it.

Backstage Construction Schedule – April 15 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 15 – 19, 2013

Please click here for general information on concrete pours.

Posted April 12, 2013

Monday, April 15

  • There will be a rebar delivery at 7:00 am.
  • A slab on grade concrete pour by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed  by 10:30 pm.

Tuesday, April 16

  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour is scheduled to begin at 12:30 pm and should be completed prior to 8:00 pm.

Wednesday, April 17

  • There will be a rebar delivery at 7:00 am.
  •  A slab on grade concrete pour by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed by 8:30 pm.

Thursday, April 11

  • A concrete pour for parking level 5 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and should be completed  by 10:30 pm.

Friday, April 12

  • There will be a rebar delivery at 7:00am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour is scheduled to begin at 12:30 pm and should be completed prior to 8:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary:

L Tower Construction Schedule April 15 – 19

This is the current construction schedule for 8 The Esplanade – L Tower –  April 15 – 19, 2013

Posted April 12, 2013

Monday, April 15

  • There will be deliveries on the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower and some ongoing cleanup of the staging area.

Tuesday, April 16

  • There will be deliveries on the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower and some ongoing cleanup of the staging area.

Wednesday, April 17

  • There will be deliveries on the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower and some ongoing cleanup of the staging area.

Thursday, April 18

  • There will be deliveries on the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower and some ongoing cleanup of the staging area

Friday, April 19

  •  There will be deliveries on the hoist throughout the day from 7:00 am.
  • There will be general work inside the L Tower and some ongoing cleanup of the staging area

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary:

Backstage Construction Schedule – April 8 – 12

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  April 8 – 12, 2013

Posted April 5, 2013

Monday, April 8

  • Dominus will receive gravel for the slab on the lowest grade base. One dump truck will be working throughout the day approximately 8  loads of  gravel.
  • There will be a rebar delivery at 11:00am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

Tuesday, April 9

  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

Wednesday, April 10

  • There will be a rebar delivery at 11:00am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

Thursday, April 11

  • A parking level pour by subcontractor Italform, 80 meters of concrete starting at 9:30am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

Friday, April 12

  • There will be a rebar delivery at 7:00am.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 9:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary April 8-12-2013

L Tower Construction Schedule April 8 – 12

This is the current construction schedule for 8 The Esplanade – L Tower –  April 8 – 12, 2013

Posted April 5, 2013

Monday, April 8

  • There will be deliveries on the hoist and there will be cleanup of the staging area.

Tuesday, April 9

  • There will be deliveries on the hoist and there will be cleanup of the staging area.

Wednesday, April 10

  • There will be deliveries on the hoist and there will be cleanup of the staging area.

Thursday, April 11

  • There will be deliveries on the hoist and there will be cleanup of the staging area.

Friday, April 12

  •  There will be deliveries on the hoist and there will be cleanup of the staging area.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary April 8-12-2013