Update – Backstage Construction Schedule – March 28 – 30

This is an update to the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 28 – 30, 2013

UPDATED March 28, 2013

Thursday, March 28 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • The long reach will be used to take material out from the site; 3 dump trucks will be taking approximately 10 loads each, for an estimated total of 30 loads
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.
  • Installation of new hoardings and covered walkway on The Esplanade.

Friday, March 29 – GOOD FRIDAY – Holiday

Saturday, March 30

  • Dominus will be doing clean up work on-site.
  • The long reach will be removed from the site. There may be some short-term interruptions to traffic access through the site during this process.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

The schedule for April 2 – 5, 2013 will be posted on March 28. Backstage & L Tower Construction Summary April 1-5-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: