L Tower Construction Schedule March 25 – 29

This is the current construction schedule for 8 The Esplanade – L Tower –  March 25 – 29, 2013

Updated March 28, 2012

MondayMarch 25

  • Demobilizing the RCS panels: i.e. lowering the structural form panels from the building and transporting them off-site. Trucks will be arriving to take the form panels away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries to the hoist throughout the day, starting at 7:00 am.  

Tuesday, March 26

  • Demobilizing the RCS panels: i.e. lowering the structural form panels from the building and transporting them off-site. Trucks will be arriving to take the form panels away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries to the hoist throughout the day, starting at 7:00 am.  

Wednesday, March 27

  • Demobilizing the RCS panels: i.e. lowering the structural form panels from the building and transporting them off-site. Trucks will be arriving to take the form panels away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries to the hoist throughout the day, starting at 7:00 am.  

Thursday, March 28

  • Demobilizing the RCS panels: i.e. lowering the structural form panels from the building and transporting them off-site. Trucks will be arriving to take the form panels away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries to the hoist throughout the day, starting at 7:00 am.  
  • Installation of new hoardings and covered walkway.

Friday, March 29 – GOOD FRIDAY – Holiday

 

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 23-29

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: