Backstage Construction Schedule – March 23 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 23 – 29, 2013

Updated – March 27, 2013

Saturday, March 23

  • Dominus will be doing clean up work on-site.

Monday, March 25

  • Dominus will receive gravel for the slab on the lowest grade base. Two dump trucks will be working throughout the day approximately 10 loads of  gravel.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.

Tuesday, March 26

  • GFL Excavating will be using the Long Reach to remove material, there will be 3 dump trucks taking up to 14 loads each for an estimated total of 42 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.

Wednesday, March 27

  • Dominus will receive gravel for the slab on the lowest grade base. Two dump trucks will be working throughout the day approximately 10 loads of  gravel.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings and slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should be completed by to 7:00 pm.

Thursday, March 28 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.

Friday, March 29 – GOOD FRIDAY – Holiday

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 23-29

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: