Backstage Construction Schedule – March 23 – 29
March 22, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for March 23 – 29, 2013
Updated – March 27, 2013
Saturday, March 23
- Dominus will be doing clean up work on-site.
Monday, March 25
- Dominus will receive gravel for the slab on the lowest grade base. Two dump trucks will be working throughout the day approximately 10 loads of gravel.
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.
Tuesday, March 26
- GFL Excavating will be using the Long Reach to remove material, there will be 3 dump trucks taking up to 14 loads each for an estimated total of 42 loads.
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.
Wednesday, March 27
- Dominus will receive gravel for the slab on the lowest grade base. Two dump trucks will be working throughout the day approximately 10 loads of gravel.
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings and slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should be completed by to 7:00 pm.
Thursday, March 28
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.
Friday, March 29 – GOOD FRIDAY – Holiday
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 23-29