Backstage Construction Schedule – March 16 – 22
March 15, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for March 16 – 22, 2013
Posted March 15, 2013
Saturday, March 16
- Dominus will be doing general labour work on-site, no machinery is scheduled to be operating.
Monday, March 18
- GFL Excavating will be using the Long Reach to remove material, there will be 4 dump trucks taking up to 12 loads each for an estimated total of 48 loads.
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.
Tuesday, March 19
- GFL Excavating will be using the Long Reach to remove material, there will be 4 dump trucks taking up to 12 loads each for an estimated total of 48 loads.
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.
Wednesday, March 20
- There will be a Reinforcing Steel delivery starting at 7:00 am.
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.
Thursday, March 21
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.
Friday, March 22
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 16-22