Backstage Construction Schedule – March 16 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 16 – 22, 2013

Posted March 15, 2013

Saturday, March 16

  • Dominus will be doing general labour work on-site, no machinery is scheduled to be operating.

Monday, March 18

  • GFL Excavating will be using the Long Reach to remove material, there will be 4 dump trucks taking up to 12 loads each for an estimated total of 48 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Tuesday, March 19

  • GFL Excavating will be using the Long Reach to remove material, there will be 4 dump trucks taking up to 12 loads each for an estimated total of 48 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Wednesday, March 20

  • There will be a Reinforcing Steel delivery starting at 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Thursday, March 21 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Friday, March 22

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 16-22

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: