Backstage Construction Schedule – March 9 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 9 – 15, 2013

Posted March 8, 2013

Saturday, March 9

  • Dominus will be operating a compressor with a 60lb breaker to break-up shale – work is scheduled to start at 9:00 am.

Monday, March 11

  • Rebar delivery is scheduled between 9:00 am and 11:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Tuesday, March 12

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Wednesday, March 13

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Thursday, March 14 

  • A rebar delivery is scheduled to occur between 9:00 am and 11:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Friday, March 15

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Update – L Tower & Backstage Construction Summary March 9 -15

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: