L Tower Construction Schedule March 4 – 8

This is the current construction schedule for 8 The Esplanade – L Tower –  March 4 – 8, 2013

Posted March 1, 2012

MondayMarch 4

  • Regular interior construction work and site activities.

Tuesday, March 5

  • Regular interior construction work and site activities. 

Wednesday, March 6

  • An 30M (cubic metre) concrete pour at level 62 – roof, scheduled to start at 1:00 pm and finish prior to 7:00 pm.

Thursday, March 7

  • A delivery of drywall is scheduled to occur after 7:00 am

Friday, March 8

  • Regular interior construction work and site activities

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Mar 4-8

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: