Backstage Construction Schedule – March 4 – 8
March 1, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for March 4 – 8, 2013
Posted March 1, 2013
Monday, March 4
- GFL Excavating will be removing material with the long reach: five (5) dump trucks are scheduled to take fourteen (14) loads each from the site for an estimated total of 70 loads.
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.
Tuesday, March 5
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.
Wednesday, March 6
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.
Thursday, March 7
- A rebar delivery is scheduled to occur between 9:00 am and 11:00 am.
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.
Friday, March 8
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click here for a downloadable construction summary: L Tower & Backstage Construction – Mar 4-8