Update – Backstage Construction Schedule – March 28 – 30

This is an update to the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 28 – 30, 2013

UPDATED March 28, 2013

Thursday, March 28 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • The long reach will be used to take material out from the site; 3 dump trucks will be taking approximately 10 loads each, for an estimated total of 30 loads
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.
  • Installation of new hoardings and covered walkway on The Esplanade.

Friday, March 29 – GOOD FRIDAY – Holiday

Saturday, March 30

  • Dominus will be doing clean up work on-site.
  • The long reach will be removed from the site. There may be some short-term interruptions to traffic access through the site during this process.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

The schedule for April 2 – 5, 2013 will be posted on March 28. Backstage & L Tower Construction Summary April 1-5-2013

Backstage Construction Schedule – March 23 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 23 – 29, 2013

Updated – March 27, 2013

Saturday, March 23

  • Dominus will be doing clean up work on-site.

Monday, March 25

  • Dominus will receive gravel for the slab on the lowest grade base. Two dump trucks will be working throughout the day approximately 10 loads of  gravel.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.

Tuesday, March 26

  • GFL Excavating will be using the Long Reach to remove material, there will be 3 dump trucks taking up to 14 loads each for an estimated total of 42 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.

Wednesday, March 27

  • Dominus will receive gravel for the slab on the lowest grade base. Two dump trucks will be working throughout the day approximately 10 loads of  gravel.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings and slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should be completed by to 7:00 pm.

Thursday, March 28 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.

Friday, March 29 – GOOD FRIDAY – Holiday

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 23-29

L Tower Construction Schedule March 25 – 29

This is the current construction schedule for 8 The Esplanade – L Tower –  March 25 – 29, 2013

Updated March 28, 2012

MondayMarch 25

  • Demobilizing the RCS panels: i.e. lowering the structural form panels from the building and transporting them off-site. Trucks will be arriving to take the form panels away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries to the hoist throughout the day, starting at 7:00 am.  

Tuesday, March 26

  • Demobilizing the RCS panels: i.e. lowering the structural form panels from the building and transporting them off-site. Trucks will be arriving to take the form panels away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries to the hoist throughout the day, starting at 7:00 am.  

Wednesday, March 27

  • Demobilizing the RCS panels: i.e. lowering the structural form panels from the building and transporting them off-site. Trucks will be arriving to take the form panels away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries to the hoist throughout the day, starting at 7:00 am.  

Thursday, March 28

  • Demobilizing the RCS panels: i.e. lowering the structural form panels from the building and transporting them off-site. Trucks will be arriving to take the form panels away. There may be short-term disruptions to traffic adjacent to the site.  
  • Deliveries to the hoist throughout the day, starting at 7:00 am.  
  • Installation of new hoardings and covered walkway.

Friday, March 29 – GOOD FRIDAY – Holiday

 

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 23-29

Backstage Construction Schedule – March 16 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 16 – 22, 2013

Posted March 15, 2013

Saturday, March 16

  • Dominus will be doing general labour work on-site, no machinery is scheduled to be operating.

Monday, March 18

  • GFL Excavating will be using the Long Reach to remove material, there will be 4 dump trucks taking up to 12 loads each for an estimated total of 48 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Tuesday, March 19

  • GFL Excavating will be using the Long Reach to remove material, there will be 4 dump trucks taking up to 12 loads each for an estimated total of 48 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Wednesday, March 20

  • There will be a Reinforcing Steel delivery starting at 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Thursday, March 21 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Friday, March 22

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 16-22

L Tower Construction Schedule March 18 – 22

This is the current construction schedule for 8 The Esplanade – L Tower –  March 18 – 22, 2013

Posted March 15, 2012

MondayMarch 18

  • Removing the concrete pump from the site.

Tuesday, March 19

  • Removing the concrete pump from the site. 

Wednesday, March 20

  • Removing the concrete pump from the site.

Thursday, March 21

  • Regular interior construction work and site activities.

Friday, March 22

  • Material and supply deliveries are scheduled all day, scheduled from 7:00 am

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 16-22

Backstage Construction Schedule – March 9 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 9 – 15, 2013

Posted March 8, 2013

Saturday, March 9

  • Dominus will be operating a compressor with a 60lb breaker to break-up shale – work is scheduled to start at 9:00 am.

Monday, March 11

  • Rebar delivery is scheduled between 9:00 am and 11:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Tuesday, March 12

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Wednesday, March 13

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Thursday, March 14 

  • A rebar delivery is scheduled to occur between 9:00 am and 11:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Friday, March 15

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Update – L Tower & Backstage Construction Summary March 9 -15

L Tower Construction Schedule March 11 – 15

This is the current construction schedule for 8 The Esplanade – L Tower –  March 11 – 15, 2013

Posted March 8, 2012

MondayMarch 11

  • Regular interior construction work and site activities.

Tuesday, March 12

  • A concrete pour at level 62 – roof, scheduled to start at 1:00 pm and finish prior to 7:00 pm. 

Wednesday, March 13

  • Regular interior construction work and site activities.

Thursday, March 14

  • Regular interior construction work and site activities.

Friday, March 15

  • A delivery for the hoist is scheduled to occur after 7:00 am. 

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Update – L Tower & Backstage Construction Summary March 9 -15

L Tower Construction Schedule March 4 – 8

This is the current construction schedule for 8 The Esplanade – L Tower –  March 4 – 8, 2013

Posted March 1, 2012

MondayMarch 4

  • Regular interior construction work and site activities.

Tuesday, March 5

  • Regular interior construction work and site activities. 

Wednesday, March 6

  • An 30M (cubic metre) concrete pour at level 62 – roof, scheduled to start at 1:00 pm and finish prior to 7:00 pm.

Thursday, March 7

  • A delivery of drywall is scheduled to occur after 7:00 am

Friday, March 8

  • Regular interior construction work and site activities

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Mar 4-8

Backstage Construction Schedule – March 4 – 8

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 4 – 8, 2013

Posted March 1, 2013

Monday, March 4

  • GFL Excavating will be removing material with the long reach: five (5) dump trucks are scheduled to take fourteen (14) loads each from the site for an estimated total of 70 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

Tuesday, March 5

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

Wednesday, March 6

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

Thursday, March 7 

  • A rebar delivery is scheduled to occur between 9:00 am and 11:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

Friday, March 8

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Mar 4-8