Update – Backstage Construction Schedule – March 28 – 30
March 28, 2013 Leave a comment
This is an update to the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for March 28 – 30, 2013
UPDATED March 28, 2013
Thursday, March 28
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- The long reach will be used to take material out from the site; 3 dump trucks will be taking approximately 10 loads each, for an estimated total of 30 loads.
- A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.
- Installation of new hoardings and covered walkway on The Esplanade.
Friday, March 29 – GOOD FRIDAY – Holiday
Saturday, March 30
- Dominus will be doing clean up work on-site.
- The long reach will be removed from the site. There may be some short-term interruptions to traffic access through the site during this process.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
The schedule for April 2 – 5, 2013 will be posted on March 28. Backstage & L Tower Construction Summary April 1-5-2013