A note on the crane at Backstage

Crane at 1 The Esplanade looking up from street level.

Crane at 1 The Esplanade looking up from street level.

A note on the crane at 1 The Esplanade – L Tower parking and Backstage condominium construction site. 

  1. The Ministry of Labour has cleared and approved the crane set up. It is has been inspected by professional engineers.
  2. The current configuration is set to the safety specifications for the crane.
  3. Safety standards decree that the crane must be able to move in the wind
      • Why? Because if the crane were locked, i.e. if it did turn in the wind, it could theoretically be at risk in extremely strong wind conditions. That it moves in the wind is part of the safety standards for crane installations of this type.
  4. The hook that hangs from the crane is left at length that balances the crane structure as per saftey requirements and Ministry standards.

If you have any further questions please email us atltowerconstructioninfo@enconsulting.ca

Update for Backstage for February 6

This is an update for Backstage condominium and L Tower parking at 1 The Esplande, for February 6, 2012.

Wednesday, February 6

There will be a rebar delivery at 7:00 am at the Backstage condo site.

This rebar delivery marks the beginning  of concrete forming on the site which will continue for the next 18 months.

L Tower Construction Schedule February 5 – 8

This is the updated construction schedule for 8 The Esplanade – L Tower –  February 5 – 8, 201320130130_132509

Posted February 4, 2012

Tuesday, February 5

  • A beam concrete pour  level 61½, starting 1:00 pm, estimated at 9 cubic meters of
    concrete which is scheduled to finish prior to 7:00 pm.

Wednesday, February 6

  • A rebar delivery scheduled to begin at 7:00 am.

Thursday, February 7

  • A column concrete pour  levels 61 – 62, starting 1:00 pm, estimated at 9 cubic meters of
    concrete which is scheduled to finish prior to 7:00 pm.

Friday, February 8

  • Nothing scheduled at this time – please check back for updates.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Update – L Tower & Backstage Construction Summary Feb 5 – 8

Backstage Construction Schedule – February 2 – 8

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 2 – 8, 2013

The site at 1 The Esplanade showing the retaining wall and the depth of the dig.

The site at 1 The Esplanade showing the retaining wall and the depth of the dig.

Updated February 4, 2013

Saturday, February 2

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 5 dump trucks taking 10 loads of material each, for an estimated  total of 50 loads.

Monday, February 4

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 5 dump trucks taking 14 loads of material each, for an estimated  total of  70 loads.

Tuesday, February 5

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 5 dump trucks taking 14 loads of material each, for an estimated  total of  70 loads.

Wednesday, February 6

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 3 to 5 dump trucks taking 14 loads of material each, for an estimated total of 42 to 70 loads.

Thursday, February 7

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 3 to 5 dump trucks taking 14 loads of material each, for an estimated total of 42 to 70 loads.

Friday, February 8 

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 3 to 5 dump trucks taking 14 loads of material each, for an estimated total of 42 to 70 loads.

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: Update – L Tower & Backstage Construction Summary Feb 5 – 8

L Tower Construction Schedule February 4 – 8

This is the current construction schedule for 8 The Esplanade – L Tower –  February 4 – 8, 2013

Posted February 1, 2012

MondayFebruary 4

  • A delivery of 3 containers of windows starting at 7:00 am.

Tuesday, February 5

  • Nothing scheduled at this time – please check back for updates. 

Wednesday, February 6

  • Nothing scheduled at this time – please check back for updates.

Thursday, February 7

  • Nothing scheduled at this time – please check back for updates.

Friday, February 8

  • Nothing scheduled at this time – please check back for updates.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 2-8