L Tower Construction Schedule February 25 – March 1
February 22, 2013 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – February 25 – March 1, 2013
Posted February 22, 2012
Monday, February 25
- 27M (cubic metre) beam concrete pour at level 62 – roof, scheduled to start at 11:00 am and finish prior to 7:00 pm.
- Material delivery for Professional Carpentry.
Tuesday, February 26
- Nothing scheduled at posting time.
Wednesday, February 27
- An 18M (cubic metre) wall concrete pour at level 62 – roof, scheduled to start at 1:00 pm and finish prior to 7:00 pm.
Thursday, February 28
- Nothing scheduled at posting time – please check back for details.
Friday, March 1
- Nothing scheduled at posting time – please check back for details.
Please note:
- There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 25 – Mar 1