L Tower Construction Schedule February 25 – March 1

This is the current construction schedule for 8 The Esplanade – L Tower –  February 25 – March 1, 2013

Posted February 22, 2012

MondayFebruary 25 

  • 27M (cubic metre) beam concrete pour at level 62 – roof, scheduled to start at 11:00 am and finish prior to 7:00 pm.
  • Material delivery for Professional Carpentry.

Tuesday, February 26

  • Nothing scheduled at posting time. 

Wednesday, February 27

  • An 18M (cubic metre) wall concrete pour at level 62 – roof, scheduled to start at 1:00 pm and finish prior to 7:00 pm.

Thursday, February 28

  • Nothing scheduled at posting time – please check back for details.

Friday, March 1

  • Nothing scheduled at posting time – please check back for details.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 25 – Mar 1

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: