L Tower Construction Schedule February 16 – 22
February 19, 2013 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – February 16 – 22, 2013
Updated February 19, 2012
Saturday, February 16
- Waterproofing the base of the hoist to begin after 9:00 am.
Monday, February 18 – FAMILY DAY HOLIDAY
- Site Closed.
Tuesday, February 19
- CANCELLED – An HVAC delivery is tentatively scheduled to begin at 7:00 am.
Wednesday, February 20
- A 9M (cubic metre) wall and column concrete pour, at levels 62 – roof, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.
Thursday, February 21
- A 9M (cubic metre) wall and column concrete pour, at levels 62 – roof, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.
Friday, February 15
- Nothing scheduled.
Please note:
- There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
- Concrete trucks must continue to operate with their engines on while concrete is being poured.
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 16-22