L Tower Construction Schedule February 16 – 22

This is the current construction schedule for 8 The Esplanade – L Tower –  February 16 – 22, 2013

Updated February 19, 2012

Saturday, February 16

  • Waterproofing the base of the hoist to begin after 9:00 am.

Monday, February 18 – FAMILY DAY HOLIDAY

  • Site Closed.

Tuesday, February 19

  • CANCELLED – An HVAC delivery is tentatively scheduled to begin at 7:00 am. 

Wednesday, February 20

  • A 9M (cubic metre) wall and column concrete pour, at levels 62 – roof, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Thursday, February 21

  • A 9M (cubic metre) wall and column concrete pour, at levels 62 – roof, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Friday, February 15

  • Nothing scheduled.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 16-22

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: