Backstage Construction Schedule – February 18 – 22
February 15, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for February 18 – 22, 2013
Posted February 15, 2013
Monday, February 18 – FAMILY DAY HOLIDAY
- Site closed for the holiday.
Tuesday, February 19
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.
Wednesday, February 20
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.
Thursday, February 21
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.
Friday, February 22
- GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
- A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 16-22