L Tower Construction Schedule February 9 – 15

This is the current construction schedule for 8 The Esplanade – L Tower –  February 9 – 15, 2013

Posted February 8, 2012

SaturdayFebruary 9

  • Hoist maintenance to begin after 9:00 am and continue through till Noon.

MondayFebruary 11

  • A delivery of drywall starting at 7:00 am.

Tuesday, February 12

  • A 9M (cubic metre) column concrete pour, at levels 61 – 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Wednesday, February 13

  • A 9M (cubic metre) column concrete pour, at levels 61 – 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Thursday, February 14

  • A 9M (cubic metre) column concrete pour, at levels 61 – 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Friday, February 15

  • A 100M (cubic metre) slab concrete pour, at level 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm..

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 9-15

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: