Backstage Construction Schedule – February 11 – 15
February 8, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for February 11 – 15, 2013
Updated February 11, 2013
Monday, February 11
- GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
Tuesday, February 12 – UPDATED
- GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
- GFL Excavating will be removing material, 3 dump trucks 14 loads each.
Wednesday, February 13
- GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
- A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.
Thursday, February 14
- GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
- A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.
Friday, February 15 – UPDATED
- GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
- A rebar delivery is scheduled to begin at 11:00 am.
- A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.
NOTES: A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control