Backstage Construction Schedule – February 11 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 11 – 15, 2013

Updated February 11, 2013

Monday, February 11

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.

Tuesday, February 12 – UPDATED 

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • GFL Excavating will be removing material, 3 dump trucks 14 loads each.

Wednesday, February 13

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm

Thursday, February 14

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  •  A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Friday, February 15 – UPDATED

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A rebar delivery is scheduled to begin at 11:00 am.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm. 

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 9-15

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: