L Tower Construction Schedule February 5 – 8

This is the updated construction schedule for 8 The Esplanade – L Tower –  February 5 – 8, 201320130130_132509

Posted February 4, 2012

Tuesday, February 5

  • A beam concrete pour  level 61½, starting 1:00 pm, estimated at 9 cubic meters of
    concrete which is scheduled to finish prior to 7:00 pm.

Wednesday, February 6

  • A rebar delivery scheduled to begin at 7:00 am.

Thursday, February 7

  • A column concrete pour  levels 61 – 62, starting 1:00 pm, estimated at 9 cubic meters of
    concrete which is scheduled to finish prior to 7:00 pm.

Friday, February 8

  • Nothing scheduled at this time – please check back for updates.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Update – L Tower & Backstage Construction Summary Feb 5 – 8

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: