Backstage Construction Schedule – February 2 – 8

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 2 – 8, 2013

The site at 1 The Esplanade showing the retaining wall and the depth of the dig.

The site at 1 The Esplanade showing the retaining wall and the depth of the dig.

Updated February 4, 2013

Saturday, February 2

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 5 dump trucks taking 10 loads of material each, for an estimated  total of 50 loads.

Monday, February 4

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 5 dump trucks taking 14 loads of material each, for an estimated  total of  70 loads.

Tuesday, February 5

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 5 dump trucks taking 14 loads of material each, for an estimated  total of  70 loads.

Wednesday, February 6

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 3 to 5 dump trucks taking 14 loads of material each, for an estimated total of 42 to 70 loads.

Thursday, February 7

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 3 to 5 dump trucks taking 14 loads of material each, for an estimated total of 42 to 70 loads.

Friday, February 8 

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 3 to 5 dump trucks taking 14 loads of material each, for an estimated total of 42 to 70 loads.

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: Update – L Tower & Backstage Construction Summary Feb 5 – 8

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: