Esplanade re-opened between Scott & Yonge

February 28, 2013  5:00 pm

The ice has stopped falling from the forming, crane and building edge at the L Tower.

The roadway has been re-opened.

Security staff will keep an eye on the situation. All the same please exercise caution traversing the roadway on The Esplanade between Scott Street and Yonge Street. 

Many thanks for your patience and understanding.

The Esplanade closed due to falling ice

 

The Esplanade between Scott Street and Yonge Street - looking west - closed due to falling ice.

The Esplanade between Scott Street and Yonge Street – looking west – closed due to falling ice.

Thursday, February 28 – 2013

Please note that due ice falling from the L Tower the construction management team for L Tower and Backstage has closed The Esplanade — between Scott Street and Yonge Street — to pedestrians and vehicles in the interests of public safety. 

We apologize for the inconvenience but safety must come first. 
  
The road will stay closed until conditions improve — please check back for updates

Backstage Construction Schedule – February 25 – March 1

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 25 – March 1, 2013

Posted February 22, 2013

Monday, February 25 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Tuesday, February 26 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Wednesday, February 27

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Thursday, February 28

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Friday, March 1

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 25 – Mar 1

L Tower Construction Schedule February 25 – March 1

This is the current construction schedule for 8 The Esplanade – L Tower –  February 25 – March 1, 2013

Posted February 22, 2012

MondayFebruary 25 

  • 27M (cubic metre) beam concrete pour at level 62 – roof, scheduled to start at 11:00 am and finish prior to 7:00 pm.
  • Material delivery for Professional Carpentry.

Tuesday, February 26

  • Nothing scheduled at posting time. 

Wednesday, February 27

  • An 18M (cubic metre) wall concrete pour at level 62 – roof, scheduled to start at 1:00 pm and finish prior to 7:00 pm.

Thursday, February 28

  • Nothing scheduled at posting time – please check back for details.

Friday, March 1

  • Nothing scheduled at posting time – please check back for details.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 25 – Mar 1

Updates for this week – concrete pours at Backstage & L Tower

The L Tower construction schedule has been updated for Wednesday, February 20 and Thursday, February 21. Please click here for details

Please note: there will be concrete pours at both L Tower and the Backstage (L Tower Parking) sites this week on Wednesday & Thursday.

There will be with increased truck traffic to service these concrete pours and some short-term delays for vehicular traffic. The construction management team apologizes for any inconvenience. 

Pedestrian access to and from Yonge Street is to be maintained.

A Paid Duty Police Officer will be on site. 

L Tower Construction Schedule February 16 – 22

This is the current construction schedule for 8 The Esplanade – L Tower –  February 16 – 22, 2013

Updated February 19, 2012

Saturday, February 16

  • Waterproofing the base of the hoist to begin after 9:00 am.

Monday, February 18 – FAMILY DAY HOLIDAY

  • Site Closed.

Tuesday, February 19

  • CANCELLED – An HVAC delivery is tentatively scheduled to begin at 7:00 am. 

Wednesday, February 20

  • A 9M (cubic metre) wall and column concrete pour, at levels 62 – roof, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Thursday, February 21

  • A 9M (cubic metre) wall and column concrete pour, at levels 62 – roof, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Friday, February 15

  • Nothing scheduled.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 16-22

Backstage Construction Schedule – February 18 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 18 – 22, 2013

Posted February 15, 2013

Monday, February 18 – FAMILY DAY HOLIDAY 

  • Site closed for the holiday.

Tuesday, February 19 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Wednesday, February 20

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Thursday, February 21

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Friday, February 22

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 16-22

Updates for Backstage Construction Schedule – February 12 & 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 11 – 15, 2013

Updated February 11, 2013

Tuesday, February 12 – UPDATED 

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • GFL Excavating will be removing material, 3 dump trucks 14 loads each.

Wednesday, February 13

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Thursday, February 14

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  •  A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Friday, February 15 – UPDATED

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A rebar delivery is scheduled to begin at 11:00 am.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm. 

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control


L Tower Construction Schedule February 9 – 15

This is the current construction schedule for 8 The Esplanade – L Tower –  February 9 – 15, 2013

Posted February 8, 2012

SaturdayFebruary 9

  • Hoist maintenance to begin after 9:00 am and continue through till Noon.

MondayFebruary 11

  • A delivery of drywall starting at 7:00 am.

Tuesday, February 12

  • A 9M (cubic metre) column concrete pour, at levels 61 – 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Wednesday, February 13

  • A 9M (cubic metre) column concrete pour, at levels 61 – 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Thursday, February 14

  • A 9M (cubic metre) column concrete pour, at levels 61 – 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Friday, February 15

  • A 100M (cubic metre) slab concrete pour, at level 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm..

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 9-15

Backstage Construction Schedule – February 11 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 11 – 15, 2013

Updated February 11, 2013

Monday, February 11

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.

Tuesday, February 12 – UPDATED 

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • GFL Excavating will be removing material, 3 dump trucks 14 loads each.

Wednesday, February 13

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm

Thursday, February 14

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  •  A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Friday, February 15 – UPDATED

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A rebar delivery is scheduled to begin at 11:00 am.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm. 

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 9-15