Backstage Construction Schedule – January 28 – February 1
January 25, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for January 28 – February 1, 2013
Posted January 25, 2013
Monday, January 28
- GFL Excavating will be preparing material using the hydraulic breaker.
- GFL Excavating will be removing material with the Long Reach excavator.
- There will be 4 dump trucks taking 14 loads of material each, for an estimated total of 56 loads
Tuesday, January 29
- GFL Excavating will be preparing material using the hydraulic breaker.
- GFL Excavating will be removing material with the Long Reach excavator.
- There will be 4 dump trucks taking 14 loads of material each, for an estimated total of 56 loads
Wednesday, January 30
- GFL Excavating will be preparing material using the hydraulic breaker.
- GFL Excavating will be removing material with the Long Reach excavator.
- There will be 4 dump trucks taking 14 loads of material each, for an estimated total of 56 loads
Thursday, January 31
- GFL Excavating will be preparing material using the hydraulic breaker.
- GFL Excavating will be removing material with the Long Reach excavator.
- There will be 4 dump trucks taking 14 loads of material each, for an estimated total of 56 loads
Friday, February 1
- GFL Excavating will be preparing material using the hydraulic breaker.
- GFL Excavating will be removing material with the Long Reach excavator.
- There will be 4 dump trucks taking 14 loads of material each, for an estimated total of 56 loads
NOTES: A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control
Please click here for a downloadable construction summary: L Tower & Backstage Construction Jan 28 – Feb 1