L Tower Construction Schedule January 21 – 25
January 18, 2013 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for January 21 – 28, 2013
Posted January 18, 2012
Monday, January 21
- A rebar (steel) delivery starting at 7:00 am.
- A delivery of HVAC components starting at 8:00 am.
- A hoist jump of 3 levels.
Tuesday, January 22
- A 54M (cubic metre) slab concrete pour at level 61 1/2, starting at 11:30 am, which is expected to finish prior to 7:00 PM.
Wednesday, January 23
- A United Drywall delivery between 7:00 am and Noon.
Thursday, January 24
- An 18M (cubic metre) wall concrete pour at level 61 1/2, starting at 1:00 pm, which is expected to finish prior to 7:00 PM.
Friday, January 25
- An 13M (cubic metre) wall concrete pour at level 61 1/2, starting at 1:00 pm, which is expected to finish prior to 7:00 PM.
Please note:
- There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
- Concrete trucks must continue to operate with their engines on while concrete is being poured.
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower & Backstage Construction Summary Jan 21 – 25