L Tower Construction Schedule January 21 – 25

This is the current construction schedule for 8 The Esplanade – L Tower – for January 21 – 28, 2013

Posted January 18, 2012

Monday, January 21

  • A rebar (steel) delivery starting at 7:00 am.
  • A delivery of HVAC components starting at 8:00 am.
  • A hoist jump of 3 levels.

Tuesday, January 22

  • A 54M (cubic metre) slab concrete pour at level 61 1/2, starting at 11:30 am, which is expected to finish prior to 7:00 PM. 

Wednesday, January 23

  • A United Drywall delivery between 7:00 am and Noon.

Thursday, January 24

  • An 18M (cubic metre) wall concrete pour at level 61 1/2, starting at 1:00 pm, which is expected to finish prior to 7:00 PM.

Friday, January 25

  • An 13M (cubic metre) wall concrete pour at level 61 1/2, starting at 1:00 pm, which is expected to finish prior to 7:00 PM.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction Summary Jan 21 – 25

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: