Backstage Construction Schedule – January 21 – 25
January 18, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for January 21 – 25, 2013
Posted January 18, 2013
Monday, January 21 – Crane installation – Vehicular Road Closure
- Italforming will be erecting tower crane today: The Esplanade will closed to vehicular traffic per hoisting permit 58988001 as approved by City of Toronto.
- Pedestrian access through the site will remain open.
- Please note: The will be significant construction traffic to the site: one 300 ton mobile crane and two support trucks and nine semi-trailer trucks bring in the tower crane and related components throughout the day.
Tuesday, January 22
- GFL Excavating will be preparing material using the hydraulic breaker.
- GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated total of 70 loads.
Wednesday, January 23
- GFL Excavating will be preparing material using the hydraulic breaker.
- GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated total of 70 loads.
Thursday, January 24
- GFL Excavating will be preparing material using the hydraulic breaker.
- GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated total of 70 loads.
Friday, January 25
- GFL Excavating will be preparing material using the hydraulic breaker.
- GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated total of 70 loads.
NOTES: A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control
Please click here for a downloadable construction summary: L Tower & Backstage Construction Summary Jan 21 – 25