L Tower Construction Schedule January 14 – 18
January 11, 2013 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for January 7 – 11, 2013
Posted January 4, 2012
Monday, January 14
- An GWBt delivery between 7:00 am and 11:00 am.
- A 9M (cubic metre) beam & wall concrete pour at level 61, starting at 1:00 pm which is expected to finish prior to 7:00 PM.
Tuesday, January 15
- No activity scheduled as of posting date. Please check back for updates.
Wednesday, January 16
- Crane lift of speed fan (safety netting) from L42 starting at 0700 am.
- A rebar (steel) delivery starting at 7:00 am.
- A 9M (cubic metre) beam & wall concrete pour at level 61, starting at 1:00 pm which is expected to finish prior to 7:00 PM.
Thursday, January 17
- A cooling tower delivery starting at 7:00 am.
Friday, January 18
- United delivery between 7:00 am and noon.
Please note:
- There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
- Concrete trucks must continue to operate with their engines on while concrete is being poured.
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.