Backstage Construction Schedule – January 14 – 18

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 14 – 18, 2013

Posted January 11, 2013

Monday, January 14

  • GFL Excavating will be preparing material using the hydraulic breaker.

Tuesday, January 15

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • There will be a delivery of reinforcing steel at 7:30 am.
  • Italforming will be bringing in a boom truck in to unload reinforcing steel.

 

Wednesday, January 16

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Italforming may be beginning to pour concrete for the crane base – to be confirmed by 5:00 pm, Monday, January 14. 
  • If the concrete pour begins there will be a concrete pump placing 120 meters of concrete.

Thursday, January 17

  • GFL Excavating will be preparing material using the hydraulic breaker.

Friday, January 18 

  • GFL Excavating will be preparing material using the hydraulic breaker.

Please note:

  • There may be some short-term disruptions to vehicular and pedestrian traffic while concrete and delivery trucks are moved into position and unloaded.
  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: