L Tower Construction Schedule January 7 – 11

This is the current construction schedule for 8 The Esplanade – L Tower – for January 7 – 11, 2013

Posted January 4, 2012

Monday, January 7

  • An HVAC component delivery starting at 7:00 am.
  • A 12M (cubic metre) beam & column concrete pour at levels 61 – 62, starting at 1:00 pm which is expected to finish prior to 7:00 PM.

Tuesday, January 8

  • A 12M (cubic metre) wall concrete pour at levels 61 – 62, starting at 1:00 pm which is expected to finish prior to 7:00 PM.

Wednesday, January 9

  • No construction activity scheduled – please check back for updates.

Thursday, January 10

  • A 27M (cubic metre) slab concrete pour at level 61 1/2, starting at 12:30 pm which is expected to finish prior to 7:00 PM.

Friday, January 11

  • A rebar (steel) delivery starting at 7:00 am.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction Jan 7-11

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: