Backstage Construction Schedule – January 7 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 7 – 11, 2013

Posted January 4 2013

Monday, January 7

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.

Tuesday, January 8

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.
  • City of Toronto contractor — OJCR Construction — is expected to be on-site to test water-main and sanitary sewers. No disruptions to traffic are anticipated.

Wednesday, January 9

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.

Thursday, January 10

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.

Friday, January 11 

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.

Please note:

  • There may be some short-term disruptions to vehicular and pedestrian traffic while dump trucks are moved into position and loaded.
  • Aecon Utilities work may also cause short-term disruptions to  to vehicular and pedestrian traffic.
  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction Jan 7-11

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: