L Tower Construction Schedule January 28 – February 1

This is the current construction schedule for 8 The Esplanade – L Tower – for January 28 – February 1, 2013

Posted January 25, 2012

Monday, January 28

  • A rebar (steel) delivery starting at 7:00 am.
  • A 54M (cubic metre) slab concrete pour at level 61 1/2, starting at 11:30 am, which is expected to finish prior to 7:00 PM. 

Tuesday, January 29

  • A delivery of windows between 7:00 am and Noon.. 
  • A rebar (steel) delivery starting at 12:30 pm.

Wednesday, January 30

  • General site work.  

Thursday, January 31

  • Crane Accident. An unfortunate accident occurred this morning in high wind conditions. A crane smashed a glass window in the L Tower. Yonge Street was required to be closed until the glass was cleaned up. No one was hurt or injured. Steps are being taken to ensure this does not happen again. The construction management team regrets any inconvenience that may have been caused.  

Friday, February 1

  • General site maintenance. The crane is broken down and this will hold up the schedule of work on the site. 

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction Jan 28 – Feb 1

Backstage Construction Schedule – January 28 – February 1

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 28 – February 1, 2013

Posted January 25, 2013

Monday, January 28

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

Tuesday, January 29

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

Wednesday, January 30

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

Thursday, January 31

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

Friday, February 1 

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction Jan 28 – Feb 1

L Tower – Saturday January 19

This is the current construction schedule for 8 The Esplanade – L Tower – for January 19, 2013

Posted January 18, 2012

Saturday, January 19

  • A delivery of 5 containers of windows between 9:00 am and 4:00 pm.

Backstage Construction Schedule – January 21 – 25

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 21 – 25, 2013

Posted January 18, 2013

Monday, January 21 – Crane installation – Vehicular Road Closure

  • Italforming will be erecting tower crane today: The Esplanade will closed to vehicular traffic per hoisting permit 58988001 as approved by City of Toronto.
  • Pedestrian access through the site will remain open.
  • Please note: The will be significant construction traffic to the site: one 300 ton mobile crane and two support trucks and nine semi-trailer trucks bring in the tower crane and related components throughout the day.

Tuesday, January 22

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

Wednesday, January 23

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

Thursday, January 24

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

Friday, January 25 

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction Summary Jan 21 – 25

L Tower Construction Schedule January 21 – 25

This is the current construction schedule for 8 The Esplanade – L Tower – for January 21 – 28, 2013

Posted January 18, 2012

Monday, January 21

  • A rebar (steel) delivery starting at 7:00 am.
  • A delivery of HVAC components starting at 8:00 am.
  • A hoist jump of 3 levels.

Tuesday, January 22

  • A 54M (cubic metre) slab concrete pour at level 61 1/2, starting at 11:30 am, which is expected to finish prior to 7:00 PM. 

Wednesday, January 23

  • A United Drywall delivery between 7:00 am and Noon.

Thursday, January 24

  • An 18M (cubic metre) wall concrete pour at level 61 1/2, starting at 1:00 pm, which is expected to finish prior to 7:00 PM.

Friday, January 25

  • An 13M (cubic metre) wall concrete pour at level 61 1/2, starting at 1:00 pm, which is expected to finish prior to 7:00 PM.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction Summary Jan 21 – 25

Backstage Construction Schedule – January 12

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 12, 2013

Posted January 11, 2013

Saturday, January 12

  • GFL Excavating will be preparing material using the hydraulic breaker.

Backstage Construction Schedule – January 14 – 18

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 14 – 18, 2013

Posted January 11, 2013

Monday, January 14

  • GFL Excavating will be preparing material using the hydraulic breaker.

Tuesday, January 15

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • There will be a delivery of reinforcing steel at 7:30 am.
  • Italforming will be bringing in a boom truck in to unload reinforcing steel.

 

Wednesday, January 16

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Italforming may be beginning to pour concrete for the crane base – to be confirmed by 5:00 pm, Monday, January 14. 
  • If the concrete pour begins there will be a concrete pump placing 120 meters of concrete.

Thursday, January 17

  • GFL Excavating will be preparing material using the hydraulic breaker.

Friday, January 18 

  • GFL Excavating will be preparing material using the hydraulic breaker.

Please note:

  • There may be some short-term disruptions to vehicular and pedestrian traffic while concrete and delivery trucks are moved into position and unloaded.
  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: 

L Tower Construction Schedule January 14 – 18

This is the current construction schedule for 8 The Esplanade – L Tower – for January 7 – 11, 2013

Posted January 4, 2012

Monday, January 14

  • An GWBt delivery between 7:00 am and 11:00 am.
  • A 9M (cubic metre) beam & wall concrete pour at level 61, starting at 1:00 pm which is expected to finish prior to 7:00 PM.

Tuesday, January 15

  • No activity scheduled as of posting date. Please check back for updates. 

Wednesday, January 16

  • Crane lift of speed fan (safety netting) from L42 starting at 0700 am.
  • A rebar (steel) delivery starting at 7:00 am.
  • A 9M (cubic metre) beam & wall concrete pour at level 61, starting at 1:00 pm which is expected to finish prior to 7:00 PM.

Thursday, January 17

  • A cooling tower delivery starting at 7:00 am.

Friday, January 18

  • United delivery between 7:00 am and noon.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: 

L Tower Construction Schedule January 7 – 11

This is the current construction schedule for 8 The Esplanade – L Tower – for January 7 – 11, 2013

Posted January 4, 2012

Monday, January 7

  • An HVAC component delivery starting at 7:00 am.
  • A 12M (cubic metre) beam & column concrete pour at levels 61 – 62, starting at 1:00 pm which is expected to finish prior to 7:00 PM.

Tuesday, January 8

  • A 12M (cubic metre) wall concrete pour at levels 61 – 62, starting at 1:00 pm which is expected to finish prior to 7:00 PM.

Wednesday, January 9

  • No construction activity scheduled – please check back for updates.

Thursday, January 10

  • A 27M (cubic metre) slab concrete pour at level 61 1/2, starting at 12:30 pm which is expected to finish prior to 7:00 PM.

Friday, January 11

  • A rebar (steel) delivery starting at 7:00 am.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction Jan 7-11

Backstage Construction Schedule – January 7 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 7 – 11, 2013

Posted January 4 2013

Monday, January 7

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.

Tuesday, January 8

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.
  • City of Toronto contractor — OJCR Construction — is expected to be on-site to test water-main and sanitary sewers. No disruptions to traffic are anticipated.

Wednesday, January 9

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.

Thursday, January 10

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.

Friday, January 11 

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.

Please note:

  • There may be some short-term disruptions to vehicular and pedestrian traffic while dump trucks are moved into position and loaded.
  • Aecon Utilities work may also cause short-term disruptions to  to vehicular and pedestrian traffic.
  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction Jan 7-11