L Tower Construction Schedule December 31 – January 4
December 28, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for December 31, 2012 – January 4, 2013
Posted December 31, 2012
Monday, December 31
- No construction activity scheduled.
Tuesday, January 1
- No construction activity scheduled.
Wednesday, January 2
- A rebar (steel) delivery starting at 7:00 am.
Thursday, January 3
- A rebar (steel) delivery starting at 7:00 am.
- A 9 cubic metre concrete pour at 9:00 am, levels 61 – 62, expected to finish prior to 7:00 pm.
Friday, January 4
- No construction activity scheduled.
Please note:
There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.