Backstage Construction Schedule – December 17 – December 21

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 17 – December 21, 2012

Updated December 17, 2012

Monday, December 17

  • GFL Excavating will be setting up long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **
  • OJCR will be tying in water lines on the Esplanade.

Tuesday, December 18

  • GFL Excavating will not be removing material. They will be operating the hydraulic breaker and preparing material, this will cause significant noise during construction hours.
  • OJCR will be tying in water lines on the Esplanade.

Wednesday, December 19

  • GFL Excavating will not be removing material. They will be operating the hydraulic breaker and preparing material.
  • OJCR will be tying in water lines on the Esplanade.

Thursday, December 20

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **

Friday, December 21

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **

NOTES: 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Continuing Sanitary Sewer & Water Main work on The Esplanade 

City of Toronto contractor — OJCR Construction — continues water main work on The Esplanade between Yonge Street and Scott Street. 

  1. Pedestrian traffic will remain open. 
  2. Eastbound Vehicular Traffic may be closed during work hours. 
  3. We have advised the City of complaints we have received in respect to their work. 

If you have further questions please contact: 

Joseph Sinopoli
Toronto Water
416-338-6526 Office

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 17 – December 21

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: