L Tower Construction Schedule December 10 – 14

This is the current construction schedule for 8 The Esplanade – L Tower – for  December 10 – 14, 2012

Updated December 14, 2012

Monday, December 10

  • CANCELLED: A 110 cubic metre, slab concrete pour at level 61, starting 8:00 am, which is not expected to finish later than 7:00 pm.
  • A rebar (steel) delivery starting at 7:00 am.

Tuesday, December 11

  • NEW: A 270 cubic metre, slab concrete pour at level 61, starting 7:30 am, which is not expected to finish later than 7:00 pm.
  • A rebar (steel) delivery starting at 7:00 am.

Wednesday, December 12

  • A rebar (steel) delivery starting at 7:00 am.

Thursday, December 13

  • A rebar (steel) delivery starting at 7:00 am.

Friday, December 14

  • NEW: A 9 cubic metre, slab concrete pour, starting at 12:30PM.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 8 – December 14


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: