L Tower Construction Schedule December 10 – 14
December 7, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for December 10 – 14, 2012
Updated December 14, 2012
Monday, December 10
- CANCELLED: A 110 cubic metre, slab concrete pour at level 61, starting 8:00 am, which is not expected to finish later than 7:00 pm.
- A rebar (steel) delivery starting at 7:00 am.
Tuesday, December 11
- NEW: A 270 cubic metre, slab concrete pour at level 61, starting 7:30 am, which is not expected to finish later than 7:00 pm.
- A rebar (steel) delivery starting at 7:00 am.
Wednesday, December 12
- A rebar (steel) delivery starting at 7:00 am.
Thursday, December 13
- A rebar (steel) delivery starting at 7:00 am.
Friday, December 14
- NEW: A 9 cubic metre, slab concrete pour, starting at 12:30PM.
Please note:
There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower & Backstage Construction December 8 – December 14