Backstage Construction Schedule – December 8 – December 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 8 – December 14, 2012

Posted December 7, 2012

Saturday, December 8

  • GFL Excavating will be assembling the long reach backhoe.

Monday, December 10

  • GFL Excavating will be operating machinery in the hole moving material in preparation for the long reach.
  • OJCR will be working on Yonge Street due to the L Tower concrete pour.

Tuesday, December 11

  • GFL Excavating will be operating machinery in the hole moving material in preparation for the long reach.
  • OJCR will be working on service connection on the Esplanade.

Wednesday, December 12

  • GFL Excavating will be setting up long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
  • OJCR will be tying in water lines on the Esplanade.

Thursday, December 13

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
  • OJCR will be tying in water lines on the Esplanade.

Friday, December 14

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
  • OJCR will be working on Yonge Street connecting the storm drain.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 8 – December 14

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: