L Tower Construction Schedule December 31 – January 4

This is the current construction schedule for 8 The Esplanade – L Tower – for  December 31, 2012 – January 4, 2013

Posted December 31, 2012

Monday, December 31

  • No construction activity scheduled.

Tuesday, January 1

  • No construction activity scheduled.

Wednesday, January 2

  • A rebar (steel) delivery starting at 7:00 am.

Thursday, January 3

  • A rebar (steel) delivery starting at 7:00 am.
  • A 9 cubic metre concrete pour at 9:00 am, levels 61 – 62, expected to finish prior to 7:00 pm.

Friday, January 4

  • No construction activity scheduled.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 31 – January 4


Happy Holidays. Joyeux Noël. Merry Christmas. Feliz Navidad.

Happy Holidays. Joyeux Noël. Merry Christmas. Feliz Navidad.

Wishing you and yours all the best for the holidays!

Backstage and L Tower Construction Schedule – December 22, 2012 – January 1, 2013

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium and 8 The Esplanade – L Tower  for December 22 – January 1, 2013

Posted December 21, 2012

Monday, December 24 – Tuesday, January 1

  • No work is scheduled for the Backstage site between December 22, 2012 and January 1, 2013.
  • No work is scheduled for the L Tower site between December 22, 2012 and January 1, 2013.
  • We have been advised that the City of Toronto’s contractor — OJCR Construction — will not be working between December 22, 2012 and January 6, 2013 and will resume water main work on The Esplanade  on January 7, 2013.

Happy Holidays and Happy New Year!

    NOTES: 

    If there is any new information we will update this website on Friday, December 28th, 2012 and January 2, 2013.

    Please click here for a downloadable construction summary: L Tower & Backstage Construction Dec 22-Jan 1

    L Tower & Backstage Schedules updated Dec 18 – 21

    The December 18 – 21, 2012, construction schedules for Backstage (including the L Tower Parking Garage) at 1 The Esplanade and the L Tower at 8 The Esplanade have been updated.

    a

    1. Please click here to go  to the Backstage Schedule 

    2. Please click here to go to the L Tower Schedule. 

    L Tower Construction Schedule December 17 – 21

    This is the current construction schedule for 8 The Esplanade – L Tower – for  December 10 – 14, 2012

    Updated December 17, 2012

    Monday, December 17

    • A rebar (steel) delivery starting at 7:00 am.
    • A 19 cubic metre concrete pour scheduled between 1 pm and 4 pm at levels 61 – 62.

    Tuesday, December 18

    • A rebar (steel) delivery starting at 7:00 am.

    Wednesday, December 19

    • Nothing scheduled as of December 17. Please check back for updates.

    Thursday, December 20

    • Nothing scheduled as of December 17. Please check back for updates.

    Friday, December 21

    • Nothing scheduled as of December 17. Please check back for updates.

    Please note:

    There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

    A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

    Please click here for a downloadable construction summary: L Tower & Backstage Construction December 17 – December 21


    Backstage Construction Schedule – December 17 – December 21

    This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 17 – December 21, 2012

    Updated December 17, 2012

    Monday, December 17

    • GFL Excavating will be setting up long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **
    • OJCR will be tying in water lines on the Esplanade.

    Tuesday, December 18

    • GFL Excavating will not be removing material. They will be operating the hydraulic breaker and preparing material, this will cause significant noise during construction hours.
    • OJCR will be tying in water lines on the Esplanade.

    Wednesday, December 19

    • GFL Excavating will not be removing material. They will be operating the hydraulic breaker and preparing material.
    • OJCR will be tying in water lines on the Esplanade.

    Thursday, December 20

    • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **

    Friday, December 21

    • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **

    NOTES: 

    ** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

    Construction activities are dependent on whether.

    Continuing Sanitary Sewer & Water Main work on The Esplanade 

    City of Toronto contractor — OJCR Construction — continues water main work on The Esplanade between Yonge Street and Scott Street. 

    1. Pedestrian traffic will remain open. 
    2. Eastbound Vehicular Traffic may be closed during work hours. 
    3. We have advised the City of complaints we have received in respect to their work. 

    If you have further questions please contact: 

    Joseph Sinopoli
    Toronto Water
    416-338-6526 Office

    Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

    Please click here for a downloadable construction summary: L Tower & Backstage Construction December 17 – December 21

    Backstage Construction Schedule – December 8 – December 14

    This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 8 – December 14, 2012

    Posted December 7, 2012

    Saturday, December 8

    • GFL Excavating will be assembling the long reach backhoe.

    Monday, December 10

    • GFL Excavating will be operating machinery in the hole moving material in preparation for the long reach.
    • OJCR will be working on Yonge Street due to the L Tower concrete pour.

    Tuesday, December 11

    • GFL Excavating will be operating machinery in the hole moving material in preparation for the long reach.
    • OJCR will be working on service connection on the Esplanade.

    Wednesday, December 12

    • GFL Excavating will be setting up long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
    • OJCR will be tying in water lines on the Esplanade.

    Thursday, December 13

    • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
    • OJCR will be tying in water lines on the Esplanade.

    Friday, December 14

    • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
    • OJCR will be working on Yonge Street connecting the storm drain.

    NOTES: 

    * Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

    Construction activities are dependent on whether.

    Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

    Please click here for a downloadable construction summary: L Tower & Backstage Construction December 8 – December 14

    L Tower Construction Schedule December 10 – 14

    This is the current construction schedule for 8 The Esplanade – L Tower – for  December 10 – 14, 2012

    Updated December 14, 2012

    Monday, December 10

    • CANCELLED: A 110 cubic metre, slab concrete pour at level 61, starting 8:00 am, which is not expected to finish later than 7:00 pm.
    • A rebar (steel) delivery starting at 7:00 am.

    Tuesday, December 11

    • NEW: A 270 cubic metre, slab concrete pour at level 61, starting 7:30 am, which is not expected to finish later than 7:00 pm.
    • A rebar (steel) delivery starting at 7:00 am.

    Wednesday, December 12

    • A rebar (steel) delivery starting at 7:00 am.

    Thursday, December 13

    • A rebar (steel) delivery starting at 7:00 am.

    Friday, December 14

    • NEW: A 9 cubic metre, slab concrete pour, starting at 12:30PM.

    Please note:

    There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

    A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

    Please click here for a downloadable construction summary: L Tower & Backstage Construction December 8 – December 14


    The Esplanade closed to vehicular traffic Dec 6 evening between Yonge Street and Scott Street.

    Please note that The Esplanade will be closed to vehicular traffic tonight — December 6, 2012 – between Yonge Street and Scott Street.

    City of Toronto subcontractor OJCR Construction was not able to complete their key task today. This is due to the Hydro One service being too close to the water main. OJCR has to tunnel under hydro.

    The City of Toronto has been notified about the street closure and it has been approved.

    We apologize for any inconvenience.

    Recap on Dec 5 Long Reach Back-hoe delivery

    UPDATE: The Long Reach Back-hoe that was scheduled to arrive Wednesday, December 5, under police escort between 6:20 am and 7:00 am. It actually arrived at 5:30 am as the City of Toronto permit stipulated that the semi-trailer float (truck) had to be out of the downtown core prior to 6:00 am. Unfortunately we did not receive accurate information on the timing of the delivery.

    On December 4 we were advised by subcontractor GFL Excavating that the back-hoe was coming early in the morning, instead of the originally and preferred plan to deliver it at midday. GFL could not get a permit for midday because City of Toronto staff considered the impact on daytime traffic would be too onerous. The permit was issued for 5 am to 6 am delivery and GFL was instructed by the City and the Police to have their large delivery truck off the site an out of the downtown by 6:00 am.

    In this case the regulations for large deliveries trumped the regulations for construction noise; the regulating bodies determined that the traffic regulations trumped the standard construction noise regulations.  

    Please click here for a revised Backstage – 1 The Esplanade construction schedule.

     
    Please click here for a revised Backstage – 1 The Esplanade construction schedule.