L Tower Construction Schedule December 3 -7

This is the current construction schedule for 8 The Esplanade – L Tower – for  December 3 – 7, 2012

Updated  December 4, 2012

Monday, December 3

  • No activity is scheduled at this time.

Tuesday, December 4

  • CANCELLED: A 110 cubic metre, slab concrete pour at level 61, starting 8:00 am, which is not expected to finish later than 7:00 pm.

Wednesday, December 5

  • No activity is scheduled at this time.

Thursday, December 6

  • A rebar (steel) delivery starting at 7:00 am.

Friday, December 7 

  • A rebar (steel) delivery starting at 7:00 am.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 3 – December 7


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: