Backstage Construction Schedule – December 3 – December 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 3 – December 7, 2012

Updated December 4, 2012

Monday, December 3 

  •  CANCELED GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach. 
  • OJCR will be working on service connection on the Esplanade.

Tuesday, December 4

  •  CANCELED GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach. 
  • OJCR will be working on service connection on the Esplanade.

Wednesday, December 5

  • The Long Reach back-hoe will be delivered to the site midday under police escort
  • OJCR will be tying in water lines on the Esplanade.

Thursday, December 6

  • GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach.
  • OJCR will be tying in water lines on the Esplanade.

Friday, December 7

  • GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach. 
  • OJCR will be tying in water lines on the Esplanade.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 3 – December 7

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: