L Tower Construction Schedule November 24 – 30

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 24 – 30, 2012

Updated  November 23, 2012

Saturday, November 24

  • Four containers of windows with delivery starting at 9:00 am and continuing to 4:00 pm.

Monday, November 26

  • A 1 cubic metre concrete pour at 9:00 am, levels 61 – 62, expected to finish prior to 7:00 pm.
  • A rebar (steel) delivery starting at 7:00 am.
  • Two containers of windows with delivery starting at 12:00 pm and continuing to 4:00 pm.
  • A delivery of window frames with delivery starting 1:00 pm and continuing to 2:00 pm.

Tuesday, November 27

  • A rebar (steel) delivery starting at 12:30 pm.

Wednesday, November 28

  • No activity is scheduled at this time.

Thursday, November 29

  • A rebar (steel) delivery starting at 7:00 am.

Friday, November 30

  • A rebar (steel) delivery starting at 7:00 am.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

 

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 26 – 30


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: